On the evening of August 11, a resident used the public session of the Mayor and Council meeting to ask about the two bocce courts at Memorial Field. The courts were overgrown and needed what the minutes call "a general tune-up." Could they be restored?
The council's answer explained more than the bocce courts. Bocce restoration had been on the Recreation Commission's list of priorities, it said, "positioned behind the completed basketball court renovation." So the work at Memorial Field runs as a queue. One project finishes, and the next one moves up. Read through the 2026 minutes and you can trace that queue over the past seven months, including where it stands as the leaves come down.
First in Line Was the Basketball Court
The basketball court was the project at the front of the queue this spring. At the May 26 council meeting, Councilwoman Davis said construction was progressing. The foundational pavement and the parking lot pathway were done, and the next phase depended on "consecutive dry weather days."
A wet late spring makes that kind of dependency tricky. The same set of minutes says the Haworth Swim Club opened Memorial Day weekend "despite poor weather." Even so, by the June 23 meeting the Recreation Commission's resurfacing was "nearly complete." When the bocce question came up on August 11, the council already called the renovation complete.
All told, the court went from base pavement to finished in about ten weeks. The Commission then had room for whatever came next.
The Dugouts Waited for Baseball to Finish
In the same June 23 report, Councilwoman Davis said the borough was "looking for a window to install dugouts without interfering with summer baseball."
That sentence shows the second rule of the queue. The field's own users set the calendar. The dugouts were ready to be scheduled in June, but summer games come first. By the September 22 meeting, the new dugouts at Memorial Field were "now operational."
Other field work moved the same way that summer. The Department of Public Works' June activity report included new sod at Little League Field and two replacement picnic tables at Terrace Street Park. None of these made headlines. Each one got done in the gaps around the season.
Smaller Jobs Moved in Parallel
Not every improvement has to wait behind the main project. Some are small enough for DPW to handle alongside its regular chipping routes and lawn maintenance.
The pickleball courts are one case. On June 23, Councilwoman Siciliano reported that "pickleball court fencing and resurfacing are expected to be completed within two weeks." That happened while the basketball court was still being finished.
The pond is another. In the same June report, DPW installed new light rings at the pond, donated by Veolia. The pond had already had a big spring. The Haworth Fishing Contest on May 9 drew record attendance, according to the May 26 minutes. A donation from the water company meant the lights never had to compete with the courts for borough money. How a project is paid for decides its place in line as much as its size does.
The Bridge Went Out to Bid
The biggest Memorial Park project of 2026 was approved before any of the summer work began. On March 24, the council approved Resolution 2026-096, which awarded CMS Construction the contract for the Memorial Park Pedestrian Bridge. The bridge links Serbeck Place to Memorial Field and replaces the existing wooden crossing.
The design itself is notable. According to the minutes, "The new bridge will be aluminum with a wood-like finish and a curved arch design." Aluminum won't need the upkeep of the wooden bridge it replaces, and the finish keeps the wooden look of the old crossing.
The bidding shows how much the price of a single small structure can vary. The borough opened six sealed bids on March 4. They ranged from $137,700 to $238,649, a gap of just over $100,000. The Borough Engineer found CMS Construction to be the lowest responsible bidder, and the contract was set at the $137,700 base bid. The winning bid came in at about 58 percent of the highest one.
The council reports from June through September do not mention the bridge again, and the posted minutes do not yet call it finished.
Grants Can Cut the Line, and Can Also Fall Through
On September 22, Councilwoman Siciliano reported that "the Borough's grant application to construct a third pickleball court was not awarded, and other funding opportunities are being explored."
A third court funded by an outside grant could have skipped the queue completely, much as the pond lights did with Veolia's donation. Without the grant, it goes back to looking for money. The same meeting brought similar news from another commission. The Shade Tree Commission's canopy preservation grant application was not awarded either, and the Commission plans to pursue a climate solutions grant, due in December, to pay for replanting. Even so, the Shade Tree Commission is putting together a fall planting list of up to 35 trees, its largest planting to date.
So in a borough of Haworth's size, two kinds of money pay for park and grounds work. Outside money arrives on its own schedule, or doesn't arrive at all. Borough money goes through the budget cycle, in the order the Recreation Commission sets.
Where the Bocce Courts Stand
That takes us back to August 11. The council did more than acknowledge the resident's question. It described the job, and the minutes record that the project requires "new ties, foundation, and a fresh crushed-oystershell playing surface."
"...will be brought back to the Recreation Commission for pricing and consideration during the upcoming budget cycle."
That is a rebuild from the ground up, not a weekend of weeding. It also has a clear next step. Bocce had been waiting behind the basketball court. After one public comment, it now has a scope of work and a place on the next budget's agenda.
Pieced together from the minutes, the queue at Memorial Field and the nearby parks looks like this as of the September 22 council meeting:
- Done: the basketball court renovation, the pickleball fencing and resurfacing, the pond light rings, and the new dugouts.
- Awarded: the Serbeck Place pedestrian bridge, contracted to CMS Construction in March.
- Up for pricing: the two-court bocce restoration, headed to the Recreation Commission for the coming budget cycle.
- Looking for funding: a third pickleball court, after its grant application was not awarded.
The Room Where the Order Gets Set
The Recreation Commission is a board of community volunteers appointed by the Mayor. It works with the DPW and Parks and Playgrounds to oversee "the upkeep, management, and responsible use of all parks, playgrounds, and recreational facilities owned by the Borough." The same volunteers run the Summer Recreation Program, Celebrate Haworth Day, the Fishing Contest, the Spring Egg Hunt, National Night Out and the Safe-Zone Halloween Celebration. So the people who rank the bocce courts against a third pickleball court are the same people setting up the egg hunt.
The Commission meets on the first Monday of each month at 7:30 PM at the Library. If the bocce pricing comes up this winter, that is where it will be discussed. The August minutes also show that a single question at a council meeting can move a project from "on the list" to "being priced."
If you're weighing how Haworth's parks and public spaces fit into your own plans, Mia Hur would be glad to walk Memorial Field with you and talk about what she sees there. Let's Connect.